Over the next couple of weeks, you will see a couple of major changes on the golf course.  On Thursday, March 23rd, Ridgetop Construction broke ground on our most recent golf course improvement project.  This project includes a new tee complex for hole #18, a reshaped fairway on #18 in hopes of seeing the entire #18 green, and a new back tee on hole #15.

If the weather cooperates, this is a rough timeline of how the project will take place.

  • Today, March 24th, all of the sod was stripped and removed from the project areas.
  • Next week all of the earth moving and shaping will take place with the goal of finishing that portion by the end of next week.
  • The following week, the week of April 3rd, the new sod should arrive and be installed completing the project by April 7th.

We will be sharing photos throughout the duration of the project, so be sure to check back for more!  Here are a few of the first pictures taken today! 